Follow your inputs through the concrete calculator, one step at a time. Lengths are converted to meters before calculating volume. Figures below show up to 12 significant digits; ≈ means approximately equal. The calculation keeps full intermediate precision, so rounding these displayed figures can give a slightly different answer.
1. Calculate each area
1. Area 1 · Slab / footing
Your dimensions and unit conversions| Dimension | Your input | Converted to meters |
|---|
| L · Length | 10 ft | 10 × 0.3048 ≈ 3.048 m |
|---|
| W · Width | 10 ft | 10 × 0.3048 ≈ 3.048 m |
|---|
| T · Thickness | 4 in | 4 × 0.0254 ≈ 0.1016 m |
|---|
Quantity: 1
Formula for one piece: Length × width × thickness.
Vsingle = 3.048 × 3.048 × 0.1016 ≈ 0.9438948864 m³
Varea = Vsingle × quantity ≈ 0.9438948864 × 1 ≈ 0.9438948864 m³
A rectangular slab with an even thickness. Measure each area without overlapping.
2. Combine areas and add reserve once
Vnet = sum of area volumes ≈ 0.9438948864 ≈ 0.9438948864 m³
Vextra = Vnet × reserve / 100 ≈ 0.9438948864 × 10% ≈ 0.09438948864 m³
Vrequired = Vnet + Vextra ≈ 0.9438948864 + 0.09438948864 ≈ 1.03828437504 m³
3. Convert the required volume
- Cubic yards: 1.03828437504 ÷ 0.764554857984 ≈ 1.35802469136 yd³.
- Cubic feet: 1.03828437504 ÷ 0.028316846592 ≈ 36.6666666667 ft³.
- Liters: 1.03828437504 × 1,000 ≈ 1038.28437504 L.
4. Calculate whole bags
Product: QUIKRETE No.1101 · 80 lb. Yield per bag: 0.6 ft³.
Y = 0.6 × 0.028316846592 ≈ 0.0169901079552 m³ per bag
Unrounded bags = Vrequired ÷ Y ≈ 1.03828437504 ÷ 0.0169901079552 ≈ 61.1111111111
Round up after combining all areas: 62 whole bags. At an exact integer boundary, insignificant floating-point noise is ignored.
5. Check supplier increments and material costs
Vbulk = Vrequired ÷ 0.764554857984 ≈ 1.35802469136 yd³
No supplier increment entered: order volume ≈ 1.35802469136 yd³.
Bag cost: no price entered.
Ready-mix cost: no price entered.
Bagged mix and ready-mix are alternatives, not quantities to add together. Supplier increments do not change the bag count. Costs exclude delivery, pumping, labor, tax and short-load charges.